This site gives you Kerala house construction tips based on different photos of house construction.Construction of a house is an achievemen...

Thursday, October 15, 2015

2. Setting out plan and digging foundation pit

Kerala House Construction Tips: This is the approved building plan for the house. I preferred a simple house plan without complication. Rooms must be spacious. Avoid structural congestion. So I cut staircase inside from house plan. I cut sit out also. No one will sit there. It normally uses for putting chapels. A small change is done to the house plan. So the space for sit out is added to the hall. We planned for a simple living by reducing kitchen utensils etc. So I avoided work area from the house plan. (But latter we felt that it was a mistake). Two bed rooms are attached. The living and dining becomes a square big space without any separation between the two. So it looks spacious. 
Foundation for house construction.

Before digging foundation, we have to set out house plan on the plot by tying threads on several wooden posts. Special care to be given to calculate actual dimensions on the actual house plan, so that we will not have hard time getting small rooms than actual dimensions from approved plan. How much we have to dig depends on the type of soil on plot. Dig foundation pit till reaching a strong earth or hard soil. If the plot is with poor or loose soil then we have go deep. If there is water bed on plot then go for pillar foundation. This plot is with normal earth condition of strong structure. No water bed or poor soil. So two feet deep and two feet wide pit is taken for foundation. Sometimes people dig more than two feet. That depends on the quality of earth on plot.

setting out the house plan on plot














digging foundation pit














At the base part, a cement concrete is done. Foundation is coming over this metal concrete. Pour water for two days.














After completing this, started putting rubble (size-stone) on to the pit. No need to use cement mortar (ചാന്ത് ) to make foundation on such type of earth. Fortunately there were no need had come to arise pillars. That has reduced the cost for it.

Placing rocks on pit


Place rubble by filling gaps with stone pieces. If you prefer to do an extra care to foundation follow these steps:

After completing foundation work, fill gap with rock waste sand and inforce water onto it to fill the gap completely. This gives extra strength to foundation.



After finishing filling stones by two feet height, then put an even layer of cement plaster on top. It is better to water for two days before starting basement.

5 comments:

  1. What is the ratio of PCC used ?

    ReplyDelete
  2. Thank You for this Low Cost and Simple Basement Could you Pls tell how to rise Construction done on that Basement

    ReplyDelete
  3. thks for your guidance.

    ReplyDelete
  4. Sir, I hope you have completed the construction of the house by now. It will be of great help (to figure out the load by looking at the building )if you share the photo of the building that you have constructed on this foundation. Thanks for sharing this.
    warm regards

    ReplyDelete